MEAT PROCESSING

CLIENT – CONFIDENTIAL

PLANT ROOM UPGRADE

LOCATION – CONFIDENTIAL

Our Client

Founded over 50 years ago, our client is one of the leading meat processing companies in the UK and Ireland.

Employing over 2,500 people and has an annual turnover in excess of €750 million.

Project Brief

MFL Mechanical were approached by their client to provide the design and installation of a turn-key plant room package for one of their facilities.

The existing steam plant on site was approaching the end of its lifecycle after many years of service, becoming inefficient, unreliable and difficult to maintain due to obsolete equipment.

We decided to partner with Arbe Integrated Engineering to design an energy efficient bespoke hot water system to suit their requirements. Delivering hot water utilising a 3 MW LTHW boiler and a packaged plate heat exchanger system for the varying factory processes.

Scope of Works

Our packaged plant room included the design, supply and installation of the following services:

  • Cochran HW29 – 3 MW LTHW Boiler
  • Boiler Flue System
  • Arbe – Bespoke DHW Packaged Plate Heat Exchanger System
  • Arbe – CWS Booster Set
  • DN200 LTHW Pipework Services
  • DN150 Gas Pipework Services
  • Gas Booster Unit
  • 60deg C Hot Water Storage Tank 4000L
  • Foodclean – PowerBoost System
  • Fulton – Electric Steam Generator
  • Interconnecting Pipework Between New Plant Room and Existing Services
  • Pipework Insulation and Stucco Cladding
  • Testing and Commissioning
  • Service and Maintenance Package

Positioning the Package

Arbe Integrated Engineering offer a range of products and services for the HVAC building services industry, ranging from heat exchangers and storage cylinders to fully packaged plant rooms and associated equipment. We were delighted to be appointed by MFL Mechanical to design, manufacture and supply the bespoke hot water package for this project.

ROB BROWNLESS
MANAGING DIRECTOR
ARBE INTEGRATED ENGINEERING

Project Complete